Migration of a process control system of a wastewater treatment plant
A client wants to migrate the old Contronic P process control system to Siemens PCS7 in his wastewater treatment plant. He is commissioning EXCO with:
- The software projection and visualization with Simatic PCS7 V7.1
- Configuration of the existing hardware components
- Network design
- Interfaces to other controllers
- Setting up of the system
- Optimization of the process
- Coordination / consultations / schedule monitoring
Implementation
With the support of EXCO, the existing basis could gradually be modernized without any breakdown of the system. This was a very large system with lots of participants and there was a major time pressure.
Technology used
Simatic PCS7 V7.1
EXCO has proven migration knowledge and lots of experience from countless migration projects.
Client
Chemical company, Germany